Deadly Collision Claims 67 Lives in U.S. Air Disaster | At Least 30 Dead and Many Injured in Stampede at Maha Kumbh Mela in India | Cambodia to Host 2025 National Chapei Dang Veng Festival from June 11-13 | Senate President Hun Sen Reflects on Cambodia’s Development and ASEAN Integration | ASEAN Secretary-General Hails Samdech Techo Hun Sen's Vision at Policy Speech | Cambodia Temporarily Bans Livestock and Meat Imports from Thailand Amid Anthrax Outbreak |
Deadly Collision Claims 67 Lives in U.S. Air Disaster | At Least 30 Dead and Many Injured in Stampede at Maha Kumbh Mela in India | Cambodia to Host 2025 National Chapei Dang Veng Festival from June 11-13 | Senate President Hun Sen Reflects on Cambodia’s Development and ASEAN Integration | ASEAN Secretary-General Hails Samdech Techo Hun Sen's Vision at Policy Speech | Cambodia Temporarily Bans Livestock and Meat Imports from Thailand Amid Anthrax Outbreak |

Phnom Penh-Sihanoukville Expressway Over 51% Complete

Phnom Penh, 4 June: The long-awaited expressway linking Phnom Penh and Sihanoukville is 51.35% complete. It is on track to be finished by the end of May 2023.

When finished, the expressway will run for almost 190 kilometres, from Village 1 of Sangkat Samrong Krom in Phnom Penh’s Khan Pou Senchey to Village 1 of Sihanoukville’s Sangkat 3. It’ll reduce the travel time between the two cities to approximately two hours.

There are just a handful of issues outstanding with the affected local communites, but the Ministry of Transport says it expects to have those resolved soon. It has also praised the construction team for continuing unabated throughout the Covid-19 pandemic.

By the time it has been finished, the expressway will have cost approximately US$2-billion, invested by the China Bridge and Road Corporation (CRBC) through Cambodian PPSHV Expressway Co., Ltd. It will be a dual carriageway, allowing a top speed of up to 120km/h along certain stretches. There will be a three metre-wide divider, and a red gravel sidewalk on each side.

The 186.86 kilometres of expressway will take you over 263 sewers, five small bridges, 80 medium-length bridges and 80 long bridges, as well as through seven traffic diversion roads, 28 intersections, 237 underpasses and 20 flyovers. Service areas, parking lots, maintenance centres and nine toll booths are also being constructed.